Proposals Bids
Requests for Proposals and Invitations to Bid
Information on current projects available for qualified and/or licensed vendors to submit proposals or bids will be posted in this section of the JCISD website.
Current Requests for Quotes
Jackson County School Technology Consortium is seeking bids for internet access for all consortium members (22 districts) including all their schools (94) and transport from the internet provider to a consortium facility. JCSTC is
soliciting one, two, three and five year bids with option to extend the contract. Please include all necessary build costs. Also, please include DDoS protection.
The Consortium service delivery location would be at one of the following:
Preferred location: 6700 Browns Lake Rd, Jackson MI 49201
Alternate location: 1226 S Wisner St., Jackson MI 49203
Bids are due by January 4, 2024, 1 PM, at which time there will be the opening of bids. Bids should be sent to:
Brad Hess, Assistant Director of Technology
Jackson County Intermediate School District
6700 Browns Lake Rd.
Jackson, MI 49201
Bids must include bidder SPIN.
-
RFQ Technical Questions Deadline – January 5, 2024 at 4:00 p.m.
-
Proposal Due Date – January 12, 2024 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – Thursday, December 21, 2023 at 4:00 p.m.
-
Proposal Due Date – January 5, 2024 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – January 5, 2024 at 4:00 p.m.
-
Proposal Due Date – January 12, 2024 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 15, 2023 at 4:00 p.m.
-
Proposal Due Date – December 22, 2023 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 15, 2023 at 4:00 p.m.
-
Proposal Due Date – December 22, 2023 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 15, 2023 at 4:00 p.m.
-
Proposal Due Date – December 22, 2023 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 15, 2023 at 4:00 p.m.
-
Proposal Due Date – December 22, 2023 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 5, 2023 at 4:00 p.m.
-
Proposal Due Date – December 12, 2023 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 5, 2023 at 4:00 p.m.
-
Proposal Due Date – December 12, 2023 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 5, 2023 at 4:00 p.m.
-
Proposal Due Date – December 12, 2023 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 5, 2023 at 4:00 p.m.
-
Proposal Due Date – December 12, 2023 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 5, 2023 at 4:00 p.m.
-
Proposal Due Date – December 12, 2023 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 5, 2023 at 4:00 p.m.
-
Proposal Due Date – December 12, 2023 at 1:00 p.m.
-
Project Completion – TBD
-
RFQ Technical Questions Deadline – December 5, 2023 at 4:00 p.m.
-
Proposal Due Date – December 12, 2023 at 1:00 p.m.
-
Project Completion – TBD
- RFQ Technical Questions Deadline – December 5, 2023 at 4:00 p.m.
- Proposal Due Date – December 12, 2023 at 1:00 p.m.
- Project Completion – TBD
Wireless Refresh Q&A
Question: I see a number of ERATE 470’s released for member districts of JCISD. The wireless portion of these all specify Cisco 9120 access points. Are these AP’s to terminate on existing Cisco controllers, and if so, is the controller function local at the district or centrally located at the ISD?
Answer: The requested APs will terminate on existing Cisco controllers that are centrally located at the ISD. Consortium members are part of an enterprise licensing agreement and as a result they purchase APs with the C9120AX-DNA-OPTOUT line item.
Question: What subscription services would you like quoted with your Palo PA-440 Firewall?
Answer: Please include the following subscriptions as optional. Threat prevention and Wildfire.
Question: What duration for the subscription services would you like quoted?
Answer: 3 year.
Question: Please confirm that you don’t need implementation services on the Palo PA-440 Firewall?
Answer: No implementation services are needed for this equipment.